Norfolk
Offshore Wind Ltd (NOW) are planning the 30 turbine Cromer offshore wind farm
some 7km off the North Norfolk coast. ETA are providing project engineering
support to NOW during the development. Key tasks include cable risk assessment
and production of detail specifications for the marine cabling of the farm.
![]() |
Cable
risk assessment A quantitative risk assessment (QRA) was provided dealing with all of the risks relating to the installation and operation of subsea power cables for energy transfer within the offshore wind farm, and from wind farm to shore.
Tender
specifications A
detailed specification was compiled to cover the installation of the
marine cables. The documentation was produced in a modular manner to
comply with EU tender guidelines and NOW's format for the tender package.
|